Milestone List


Milestone
number
Milestone title WP number Lead
beneficiary
Due Date (in
months)
Means of verification
MS1 Kick Off meeting WP1 1 - EGP 1 Release of the Meeting minutes.
MS2 Website WP6 2 - CNR 6 Website up and running, available on line for public
access.
MS3 Final Conference WP6 1 - EGP 33 Opening of the of project conference.
MS4 Start of Drilling
Phase
WP2 1 - EGP 18 Drilling pad and preparation completed; first activity on the well head, as from the daily report of the drilling crew.
MS5 End of Drilling
Phase
WP2 1 - EGP 31 Drilling string removed, Well head closed and pressurized, as from the daily report of the drilling crew.
MS6 High temperature
and pressure tool
available
WP3 7 -
STIFTELSEN
SINTEF
18 Measurement tool up an running, as from laboratory report.
MS7 Seismicity network
in operation
WP4 1 - EGP 6 Seismicity sensors, data acquisition and updated software up and running;recording the first event.
MS8 VSP & Piggy
Back Seismic
data acquisition
completed
WP4 1 - EGP 8 Termination of new seismic data acquisition, interpretation and elaboration phase (VPS, piggy back); releases of reports D4.1, D4.2 and D4.3
MS9 Identification of
drilling target
WP4 1 - EGP 18 The depth of drilling target (with expected error) is identified. Release of report D4.4 (first stage).
MS10 Regional flow
model
WP5 3 - RWTH
AACHEN
6 Release of the model, validated against geophysical observation data.
MS11 Venelle 2 well
model
WP5 3 - RWTH
AACHEN
32 Release of the model, validated against geophysical observation data and drilling logs.
MS12 Update of the
models for
supercritical
situation
WP5 1 - EGP 32 Release of the model, validated against geophysical observation data, drilling logs and thermodynamic behaviour of the well.
MS13 Project End WP1 1 - EGP 36 Release of the last EB Meeting minutes.
MS14 Web Project
Conference
WP6 2 - CNR 8 D6.6 Web Project Conference, where project design is shared with participants at similar projects in Iceland and Japan, at month 8